| 
 |  | HB4383 Engrossed |  | LRB102 22689 SPS 31835 b |  
  | 
 | 
| 1 |  |  AN ACT concerning regulation.
 | 
| 2 |  |  Be it enacted by the People of the State of Illinois,
 | 
| 3 |  | represented in the General Assembly:
 | 
| 4 |  |  Section 5. The Public Utilities Act is amended by changing  | 
| 5 |  | Sections 8-406 and 8-406.1 as follows:
 | 
| 6 |  |  (220 ILCS 5/8-406) (from Ch. 111 2/3, par. 8-406) | 
| 7 |  |  Sec. 8-406. Certificate of public convenience and  | 
| 8 |  | necessity.  | 
| 9 |  |  (a) No public utility not owning any city or village
 | 
| 10 |  | franchise nor engaged in performing any public service or in  | 
| 11 |  | furnishing any
product or commodity within this State as of  | 
| 12 |  | July 1, 1921 and not
possessing a certificate of
public  | 
| 13 |  | convenience and necessity from the Illinois Commerce  | 
| 14 |  | Commission,
the State Public Utilities Commission, or
the  | 
| 15 |  | Public Utilities Commission, at the time Public Act 84-617  | 
| 16 |  | this amendatory Act of 1985 goes
into effect (January 1,  | 
| 17 |  | 1986), shall transact any business in this State until it  | 
| 18 |  | shall have
obtained a certificate from the Commission that  | 
| 19 |  | public convenience and
necessity require the transaction of  | 
| 20 |  | such business. A certificate of public convenience and  | 
| 21 |  | necessity requiring the transaction of public utility business  | 
| 22 |  | in any area of this State shall include authorization to the  | 
| 23 |  | public utility receiving the certificate of public convenience  | 
     | 
 |  | HB4383 Engrossed | - 2 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  | and necessity to construct such plant, equipment, property, or  | 
| 2 |  | facility as is provided for under the terms and conditions of  | 
| 3 |  | its tariff and as is necessary to provide utility service and  | 
| 4 |  | carry out the transaction of public utility business by the  | 
| 5 |  | public utility in the designated area. | 
| 6 |  |  (b) No public utility shall begin the construction of any  | 
| 7 |  | new plant,
equipment, property, or facility which is not in  | 
| 8 |  | substitution of any
existing plant, equipment, property, or  | 
| 9 |  | facility, or any extension or
alteration thereof or in  | 
| 10 |  | addition thereto,
unless and until it shall have obtained from  | 
| 11 |  | the
Commission a certificate that public convenience and  | 
| 12 |  | necessity require such
construction. Whenever after a hearing  | 
| 13 |  | the Commission determines that any
new construction or the  | 
| 14 |  | transaction of any business by a public utility will
promote  | 
| 15 |  | the public convenience and is necessary thereto, it shall have  | 
| 16 |  | the
power to issue certificates of public convenience and  | 
| 17 |  | necessity. The
Commission shall determine that proposed  | 
| 18 |  | construction will promote the
public convenience and necessity  | 
| 19 |  | only if the utility demonstrates: (1) that the
proposed  | 
| 20 |  | construction is necessary to provide adequate, reliable, and
 | 
| 21 |  | efficient service to its customers and is the
least-cost means  | 
| 22 |  | of
satisfying the service needs of its customers or that the  | 
| 23 |  | proposed construction will promote the development of an  | 
| 24 |  | effectively competitive electricity market that operates  | 
| 25 |  | efficiently, is equitable to all customers, and is the least  | 
| 26 |  | cost means of satisfying those objectives;
(2) that the  | 
     | 
 |  | HB4383 Engrossed | - 3 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  | utility is capable of efficiently managing and
supervising the  | 
| 2 |  | construction process and has taken sufficient action to
ensure  | 
| 3 |  | adequate and efficient construction and supervision thereof;  | 
| 4 |  | and (3)
that the utility is capable of financing the proposed  | 
| 5 |  | construction without
significant adverse financial  | 
| 6 |  | consequences for the utility or its
customers. | 
| 7 |  |  (b-5) As used in this subsection (b-5): | 
| 8 |  |  "Qualifying direct current applicant" means an entity that  | 
| 9 |  | seeks to provide direct current bulk transmission service for  | 
| 10 |  | the purpose of transporting electric energy in interstate  | 
| 11 |  | commerce. | 
| 12 |  |  "Qualifying direct current project" means a high voltage  | 
| 13 |  | direct current electric service line that crosses at least one  | 
| 14 |  | Illinois border, the Illinois portion of which is physically  | 
| 15 |  | located within the region of the Midcontinent Independent  | 
| 16 |  | System Operator, Inc., or its successor organization, and runs  | 
| 17 |  | through the counties of Pike, Scott, Greene, Macoupin,  | 
| 18 |  | Montgomery, Christian, Shelby, Cumberland, and Clark, is  | 
| 19 |  | capable of transmitting electricity at voltages of 345  | 
| 20 |  | kilovolts 345kv or above, and may also include associated  | 
| 21 |  | interconnected alternating current interconnection facilities  | 
| 22 |  | in this State that are part of the proposed project and  | 
| 23 |  | reasonably necessary to connect the project with other  | 
| 24 |  | portions of the grid. | 
| 25 |  |  Notwithstanding any other provision of this Act, a  | 
| 26 |  | qualifying direct current applicant that does not own,  | 
     | 
 |  | HB4383 Engrossed | - 4 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  | control, operate, or manage, within this State, any plant,  | 
| 2 |  | equipment, or property used or to be used for the transmission  | 
| 3 |  | of electricity at the time of its application or of the  | 
| 4 |  | Commission's order may file an application on or before  | 
| 5 |  | December 31, 2023 with the Commission pursuant to this Section  | 
| 6 |  | or Section 8-406.1 for, and the Commission may grant, a  | 
| 7 |  | certificate of public convenience and necessity to construct,  | 
| 8 |  | operate, and maintain a qualifying direct current project. The  | 
| 9 |  | qualifying direct current applicant may also include in the  | 
| 10 |  | application requests for authority under Section 8-503. The  | 
| 11 |  | Commission shall grant the application for a certificate of  | 
| 12 |  | public convenience and necessity and requests for authority  | 
| 13 |  | under Section 8-503 if it finds that the qualifying direct  | 
| 14 |  | current applicant and the proposed qualifying direct current  | 
| 15 |  | project satisfy the requirements of this subsection and  | 
| 16 |  | otherwise satisfy the criteria of this Section or Section  | 
| 17 |  | 8-406.1 and the criteria of Section 8-503, as applicable to  | 
| 18 |  | the application and to the extent such criteria are not  | 
| 19 |  | superseded by the provisions of this subsection. The  | 
| 20 |  | Commission's order on the application for the certificate of  | 
| 21 |  | public convenience and necessity shall also include the  | 
| 22 |  | Commission's findings and determinations on the request or  | 
| 23 |  | requests for authority pursuant to Section 8-503. Prior to  | 
| 24 |  | filing its application under either this Section or Section  | 
| 25 |  | 8-406.1, the qualifying direct current applicant shall conduct  | 
| 26 |  | 3 public meetings in accordance with subsection (h) of this  | 
     | 
 |  | HB4383 Engrossed | - 5 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  | Section. If the qualifying direct current applicant  | 
| 2 |  | demonstrates in its application that the proposed qualifying  | 
| 3 |  | direct current project is designed to deliver electricity to a  | 
| 4 |  | point or points on the electric transmission grid in either or  | 
| 5 |  | both the PJM Interconnection, LLC or the Midcontinent  | 
| 6 |  | Independent System Operator, Inc., or their respective  | 
| 7 |  | successor organizations, the proposed qualifying direct  | 
| 8 |  | current project shall be deemed to be, and the Commission  | 
| 9 |  | shall find it to be, for public use. If the qualifying direct  | 
| 10 |  | current applicant further demonstrates in its application that  | 
| 11 |  | the proposed transmission project has a capacity of 1,000  | 
| 12 |  | megawatts or larger and a voltage level of 345 kilovolts or  | 
| 13 |  | greater, the proposed transmission project shall be deemed to  | 
| 14 |  | satisfy, and the Commission shall find that it satisfies, the  | 
| 15 |  | criteria stated in item (1) of subsection (b) of this Section  | 
| 16 |  | or in paragraph (1) of subsection (f) of Section 8-406.1, as  | 
| 17 |  | applicable to the application, without the taking of  | 
| 18 |  | additional evidence on these criteria. Prior to the transfer  | 
| 19 |  | of functional control of any transmission assets to a regional  | 
| 20 |  | transmission organization, a qualifying direct current  | 
| 21 |  | applicant shall request Commission approval to join a regional  | 
| 22 |  | transmission organization in an application filed pursuant to  | 
| 23 |  | this subsection (b-5) or separately pursuant to Section 7-102  | 
| 24 |  | of this Act. The Commission may grant permission to a  | 
| 25 |  | qualifying direct current applicant to join a regional  | 
| 26 |  | transmission organization if it finds that the membership, and  | 
     | 
 |  | HB4383 Engrossed | - 6 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  | associated transfer of functional control of transmission  | 
| 2 |  | assets, benefits Illinois customers in light of the attendant  | 
| 3 |  | costs and is otherwise in the public interest. Nothing in this  | 
| 4 |  | subsection (b-5) requires a qualifying direct current  | 
| 5 |  | applicant to join a regional transmission organization.  | 
| 6 |  | Nothing in this subsection (b-5) requires the owner or  | 
| 7 |  | operator of a high voltage direct current transmission line  | 
| 8 |  | that is not a qualifying direct current project to obtain a  | 
| 9 |  | certificate of public convenience and necessity to the extent  | 
| 10 |  | it is not otherwise required by this Section 8-406 or any other  | 
| 11 |  | provision of this Act.  | 
| 12 |  |  (c) After September 11, 1987 (the effective date of Public  | 
| 13 |  | Act 85-377) this amendatory Act of 1987, no
construction shall  | 
| 14 |  | commence on any new nuclear
power plant to be located within  | 
| 15 |  | this State, and no certificate of public
convenience and  | 
| 16 |  | necessity or other authorization shall be issued therefor
by  | 
| 17 |  | the Commission, until the Director of the Illinois  | 
| 18 |  | Environmental
Protection Agency finds that the United States  | 
| 19 |  | Government, through its
authorized agency, has identified and  | 
| 20 |  | approved a demonstrable technology or
means for the disposal  | 
| 21 |  | of high level nuclear waste, or until such
construction has  | 
| 22 |  | been specifically approved by a statute enacted by the General
 | 
| 23 |  | Assembly. | 
| 24 |  |  As used in this Section, "high level nuclear waste" means  | 
| 25 |  | those aqueous
wastes resulting from the operation of the first  | 
| 26 |  | cycle of the solvent
extraction system or equivalent and the  | 
     | 
 |  | HB4383 Engrossed | - 7 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  | concentrated wastes of the
subsequent extraction cycles or  | 
| 2 |  | equivalent in a facility for reprocessing
irradiated reactor  | 
| 3 |  | fuel and shall include spent fuel assemblies prior to
fuel  | 
| 4 |  | reprocessing. | 
| 5 |  |  (d) In making its determination under subsection (b) of  | 
| 6 |  | this Section, the Commission shall attach primary
weight to  | 
| 7 |  | the cost or cost savings to the customers of the utility. The
 | 
| 8 |  | Commission may consider any or all factors which will or may  | 
| 9 |  | affect such
cost or cost savings, including the public  | 
| 10 |  | utility's engineering judgment regarding the materials used  | 
| 11 |  | for construction. | 
| 12 |  |  (e) The Commission may issue a temporary certificate which  | 
| 13 |  | shall remain
in force not to exceed one year in cases of  | 
| 14 |  | emergency, to assure maintenance
of adequate service or to  | 
| 15 |  | serve particular customers, without notice or
hearing, pending  | 
| 16 |  | the determination of an application for a certificate, and
may  | 
| 17 |  | by regulation exempt from the requirements of this Section  | 
| 18 |  | temporary
acts or operations for which the issuance of a  | 
| 19 |  | certificate will not be
required in the public interest. | 
| 20 |  |  A public utility shall not be required to obtain but may  | 
| 21 |  | apply for and
obtain a certificate of public convenience and  | 
| 22 |  | necessity pursuant to this
Section with respect to any matter  | 
| 23 |  | as to which it has received the
authorization or order of the  | 
| 24 |  | Commission under the Electric Supplier Act,
and any such  | 
| 25 |  | authorization or order granted a public utility by the
 | 
| 26 |  | Commission under that Act shall as between public utilities be  | 
     | 
 |  | HB4383 Engrossed | - 8 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  | deemed to
be, and shall have except as provided in that Act the  | 
| 2 |  | same force and effect
as, a certificate of public convenience  | 
| 3 |  | and necessity issued pursuant to this
Section. | 
| 4 |  |  No electric cooperative shall be made or shall become a  | 
| 5 |  | party to or shall
be entitled to be heard or to otherwise  | 
| 6 |  | appear or participate in any
proceeding initiated under this  | 
| 7 |  | Section for authorization of power plant
construction and as  | 
| 8 |  | to matters as to which a remedy is available under the
Electric  | 
| 9 |  | Supplier Act. | 
| 10 |  |  (f) Such certificates may be altered or modified by the  | 
| 11 |  | Commission, upon
its own motion or upon application by the  | 
| 12 |  | person or corporation affected.
Unless exercised within a  | 
| 13 |  | period of 2 years from the grant thereof,
authority conferred  | 
| 14 |  | by a certificate of convenience and necessity issued by
the  | 
| 15 |  | Commission shall be null and void. | 
| 16 |  |  No certificate of public convenience and necessity shall  | 
| 17 |  | be construed as
granting a monopoly or an exclusive privilege,  | 
| 18 |  | immunity or franchise. | 
| 19 |  |  (g) A public utility that undertakes any of the actions  | 
| 20 |  | described in items (1) through (3) of this subsection (g) or  | 
| 21 |  | that has obtained approval pursuant to Section 8-406.1 of this  | 
| 22 |  | Act shall not be required to comply with the requirements of  | 
| 23 |  | this Section to the extent such requirements otherwise would  | 
| 24 |  | apply. For purposes of this Section and Section 8-406.1 of  | 
| 25 |  | this Act, "high voltage electric service line" means an  | 
| 26 |  | electric line having a design voltage of 100,000 or more. For  | 
     | 
 |  | HB4383 Engrossed | - 9 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  | purposes of this subsection (g), a public utility may do any of  | 
| 2 |  | the following: | 
| 3 |  |   (1) replace or upgrade any existing high voltage  | 
| 4 |  |  electric service line and related facilities,  | 
| 5 |  |  notwithstanding its length; | 
| 6 |  |   (2) relocate any existing high voltage electric  | 
| 7 |  |  service line and related facilities, notwithstanding its  | 
| 8 |  |  length, to accommodate construction or expansion of a  | 
| 9 |  |  roadway or other transportation infrastructure; or | 
| 10 |  |   (3) construct a high voltage electric service line and  | 
| 11 |  |  related facilities that is constructed solely to serve a  | 
| 12 |  |  single customer's premises or to provide a generator  | 
| 13 |  |  interconnection to the public utility's transmission  | 
| 14 |  |  system and that will pass under or over the premises owned  | 
| 15 |  |  by the customer or generator to be served or under or over  | 
| 16 |  |  premises for which the customer or generator has secured  | 
| 17 |  |  the necessary right of way.  | 
| 18 |  |  (h) A public utility seeking to construct a high-voltage  | 
| 19 |  | electric service line and related facilities (Project) must  | 
| 20 |  | show that the utility has held a minimum of 2 pre-filing public  | 
| 21 |  | meetings to receive public comment concerning the Project in  | 
| 22 |  | each county where the Project is to be located, no earlier than  | 
| 23 |  | 6 months prior to filing an application for a certificate of  | 
| 24 |  | public convenience and necessity from the Commission. Notice  | 
| 25 |  | of the public meeting shall be published in a newspaper of  | 
| 26 |  | general circulation within the affected county once a week for  | 
     | 
 |  | HB4383 Engrossed | - 10 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  | 3 consecutive weeks, beginning no earlier than one month prior  | 
| 2 |  | to the first public meeting. If the Project traverses 2  | 
| 3 |  | contiguous counties and where in one county the transmission  | 
| 4 |  | line mileage and number of landowners over whose property the  | 
| 5 |  | proposed route traverses is one-fifth or less of the  | 
| 6 |  | transmission line mileage and number of such landowners of the  | 
| 7 |  | other county, then the utility may combine the 2 pre-filing  | 
| 8 |  | meetings in the county with the greater transmission line  | 
| 9 |  | mileage and affected landowners. All other requirements  | 
| 10 |  | regarding pre-filing meetings shall apply in both counties.  | 
| 11 |  | Notice of the public meeting, including a description of the  | 
| 12 |  | Project, must be provided in writing to the clerk of each  | 
| 13 |  | county where the Project is to be located. A representative of  | 
| 14 |  | the Commission shall be invited to each pre-filing public  | 
| 15 |  | meeting. | 
| 16 |  |  (i) For applications filed after August 18, 2015 (the  | 
| 17 |  | effective date of Public Act 99-399) this amendatory Act of  | 
| 18 |  | the 99th General Assembly, the Commission shall, by certified  | 
| 19 |  | mail, registered mail notify each owner of record of land, as  | 
| 20 |  | identified in the records of the relevant county tax assessor,  | 
| 21 |  | included in the right-of-way over which the utility seeks in  | 
| 22 |  | its application to construct a high-voltage electric line of  | 
| 23 |  | the time and place scheduled for the initial hearing on the  | 
| 24 |  | public utility's application. The utility shall reimburse the  | 
| 25 |  | Commission for the cost of the postage and supplies incurred  | 
| 26 |  | for mailing the notice. | 
     | 
 |  | HB4383 Engrossed | - 11 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  | (Source: P.A. 102-609, eff. 8-27-21; 102-662, eff. 9-15-21;  | 
| 2 |  | revised 10-21-21.)
 | 
| 3 |  |  (220 ILCS 5/8-406.1) | 
| 4 |  |  Sec. 8-406.1. Certificate of public convenience and  | 
| 5 |  | necessity; expedited procedure. | 
| 6 |  |  (a) A public utility may apply for a certificate of public  | 
| 7 |  | convenience and necessity pursuant to this Section for the  | 
| 8 |  | construction of any new high voltage electric service line and  | 
| 9 |  | related facilities (Project). To facilitate the expedited  | 
| 10 |  | review process of an application filed pursuant to this  | 
| 11 |  | Section, an application shall include all of the following: | 
| 12 |  |   (1) Information in support of the application that  | 
| 13 |  |  shall include the following: | 
| 14 |  |    (A) A detailed description of the Project,  | 
| 15 |  |  including location maps and plot plans to scale  | 
| 16 |  |  showing all major components. | 
| 17 |  |    (B) The following engineering data: | 
| 18 |  |     (i) a detailed Project description including: | 
| 19 |  |      (I) name and destination of the Project; | 
| 20 |  |      (II) design voltage rating (kV); | 
| 21 |  |      (III) operating voltage rating (kV); and | 
| 22 |  |      (IV) normal peak operating current rating; | 
| 23 |  |     (ii) a conductor, structures, and substations  | 
| 24 |  |  description including: | 
| 25 |  |      (I) conductor size and type; | 
     | 
 |  | HB4383 Engrossed | - 12 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  |      (II) type of structures; | 
| 2 |  |      (III) height of typical structures; | 
| 3 |  |      (IV) an explanation why these structures  | 
| 4 |  |  were selected; | 
| 5 |  |      (V) dimensional drawings of the typical  | 
| 6 |  |  structures to be used in the Project; and | 
| 7 |  |      (VI) a list of the names of all new (and  | 
| 8 |  |  existing if applicable) substations or  | 
| 9 |  |  switching stations that will be associated  | 
| 10 |  |  with the proposed new high voltage electric  | 
| 11 |  |  service line; | 
| 12 |  |     (iii) the location of the site and  | 
| 13 |  |  right-of-way including: | 
| 14 |  |      (I) miles of right-of-way; | 
| 15 |  |      (II) miles of circuit; | 
| 16 |  |      (III) width of the right-of-way; and | 
| 17 |  |      (IV) a brief description of the area  | 
| 18 |  |  traversed by the proposed high voltage  | 
| 19 |  |  electric service line, including a description  | 
| 20 |  |  of the general land uses in the area and the  | 
| 21 |  |  type of terrain crossed by the proposed line; | 
| 22 |  |     (iv) assumptions, bases, formulae, and methods  | 
| 23 |  |  used in the development and preparation of the  | 
| 24 |  |  diagrams and accompanying data, and a technical  | 
| 25 |  |  description providing the following information: | 
| 26 |  |      (I) number of circuits, with  | 
     | 
 |  | HB4383 Engrossed | - 13 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  |  identification as to whether the circuit is  | 
| 2 |  |  overhead or underground; | 
| 3 |  |      (II) the operating voltage and frequency;  | 
| 4 |  |  and | 
| 5 |  |      (III) conductor size and type and number  | 
| 6 |  |  of conductors per phase; | 
| 7 |  |     (v) if the proposed interconnection is an  | 
| 8 |  |  overhead line, the following additional  | 
| 9 |  |  information also must be provided: | 
| 10 |  |      (I) the wind and ice loading design  | 
| 11 |  |  parameters; | 
| 12 |  |      (II) a full description and drawing of a  | 
| 13 |  |  typical supporting structure, including  | 
| 14 |  |  strength specifications; | 
| 15 |  |      (III) structure spacing with typical  | 
| 16 |  |  ruling and maximum spans; | 
| 17 |  |      (IV) conductor (phase) spacing; and | 
| 18 |  |      (V) the designed line-to-ground and  | 
| 19 |  |  conductor-side clearances; | 
| 20 |  |     (vi) if an underground or underwater  | 
| 21 |  |  interconnection is proposed, the following  | 
| 22 |  |  additional information also must be provided: | 
| 23 |  |      (I) burial depth; | 
| 24 |  |      (II) type of cable and a description of  | 
| 25 |  |  any required supporting equipment, such as  | 
| 26 |  |  insulation medium pressurizing or forced  | 
     | 
 |  | HB4383 Engrossed | - 14 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  |  cooling; | 
| 2 |  |      (III) cathodic protection scheme; and | 
| 3 |  |      (IV) type of dielectric fluid and  | 
| 4 |  |  safeguards used to limit potential spills in  | 
| 5 |  |  waterways; | 
| 6 |  |     (vii) technical diagrams that provide  | 
| 7 |  |  clarification of any item under this item (1)  | 
| 8 |  |  should be included; and | 
| 9 |  |     (viii) applicant shall provide and identify a  | 
| 10 |  |  primary right-of-way and one or more alternate  | 
| 11 |  |  rights-of-way for the Project as part of the  | 
| 12 |  |  filing. To the extent applicable, for each  | 
| 13 |  |  right-of-way, an applicant shall provide the  | 
| 14 |  |  information described in this subsection (a). Upon  | 
| 15 |  |  a showing of good cause in its filing, an  | 
| 16 |  |  applicant may be excused from providing and  | 
| 17 |  |  identifying alternate rights-of-way. | 
| 18 |  |   (2) An application fee of $100,000, which shall be  | 
| 19 |  |  paid into the Public Utility Fund at the time the Chief  | 
| 20 |  |  Clerk of the Commission deems it complete and accepts the  | 
| 21 |  |  filing. | 
| 22 |  |   (3) Information showing that the utility has held a  | 
| 23 |  |  minimum of 3 pre-filing public meetings to receive public  | 
| 24 |  |  comment concerning the Project in each county where the  | 
| 25 |  |  Project is to be located, no earlier than 6 months prior to  | 
| 26 |  |  the filing of the application. Notice of the public  | 
     | 
 |  | HB4383 Engrossed | - 15 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  |  meeting shall be published in a newspaper of general  | 
| 2 |  |  circulation within the affected county once a week for 3  | 
| 3 |  |  consecutive weeks, beginning no earlier than one month  | 
| 4 |  |  prior to the first public meeting. If the Project  | 
| 5 |  |  traverses 2 contiguous counties and where in one county  | 
| 6 |  |  the transmission line mileage and number of landowners  | 
| 7 |  |  over whose property the proposed route traverses is 1/5 or  | 
| 8 |  |  less of the transmission line mileage and number of such  | 
| 9 |  |  landowners of the other county, then the utility may  | 
| 10 |  |  combine the 3 pre-filing meetings in the county with the  | 
| 11 |  |  greater transmission line mileage and affected landowners.  | 
| 12 |  |  All other requirements regarding pre-filing meetings shall  | 
| 13 |  |  apply in both counties. Notice of the public meeting,  | 
| 14 |  |  including a description of the Project, must be provided  | 
| 15 |  |  in writing to the clerk of each county where the Project is  | 
| 16 |  |  to be located. A representative of the Commission shall be  | 
| 17 |  |  invited to each pre-filing public meeting. | 
| 18 |  |  For applications filed after the effective date of this  | 
| 19 |  | amendatory Act of the 99th General Assembly, the Commission  | 
| 20 |  | shall, by certified mail, registered mail notify each owner of  | 
| 21 |  | record of the land, as identified in the records of the  | 
| 22 |  | relevant county tax assessor, included in the primary or  | 
| 23 |  | alternate rights-of-way identified in the utility's  | 
| 24 |  | application of the time and place scheduled for the initial  | 
| 25 |  | hearing upon the public utility's application. The utility  | 
| 26 |  | shall reimburse the Commission for the cost of the postage and  | 
     | 
 |  | HB4383 Engrossed | - 16 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  | supplies incurred for mailing the notice.  | 
| 2 |  |  (b) At the first status hearing the administrative law  | 
| 3 |  | judge shall set a schedule for discovery that shall take into  | 
| 4 |  | consideration the expedited nature of the proceeding.  | 
| 5 |  |  (c) Nothing in this Section prohibits a utility from  | 
| 6 |  | requesting, or the Commission from approving, protection of  | 
| 7 |  | confidential or proprietary information under applicable law.  | 
| 8 |  | The public utility may seek confidential protection of any of  | 
| 9 |  | the information provided pursuant to this Section, subject to  | 
| 10 |  | Commission approval. | 
| 11 |  |  (d) The public utility shall publish notice of its  | 
| 12 |  | application in the official State newspaper within 10 days  | 
| 13 |  | following the date of the application's filing. | 
| 14 |  |  (e) The public utility shall establish a dedicated website  | 
| 15 |  | for the Project 3 weeks prior to the first public meeting and  | 
| 16 |  | maintain the website until construction of the Project is  | 
| 17 |  | complete. The website address shall be included in all public  | 
| 18 |  | notices. | 
| 19 |  |  (f) The Commission shall, after notice and hearing, grant  | 
| 20 |  | a certificate of public convenience and necessity filed in  | 
| 21 |  | accordance with the requirements of this Section if, based  | 
| 22 |  | upon the application filed with the Commission and the  | 
| 23 |  | evidentiary record, it finds the Project will promote the  | 
| 24 |  | public convenience and necessity and that all of the following  | 
| 25 |  | criteria are satisfied: | 
| 26 |  |   (1) That the Project is necessary to provide adequate,  | 
     | 
 |  | HB4383 Engrossed | - 17 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  |  reliable, and efficient service to the public utility's  | 
| 2 |  |  customers and is the least-cost means of satisfying the  | 
| 3 |  |  service needs of the public utility's customers or that  | 
| 4 |  |  the Project will promote the development of an effectively  | 
| 5 |  |  competitive electricity market that operates efficiently,  | 
| 6 |  |  is equitable to all customers, and is the least cost means  | 
| 7 |  |  of satisfying those objectives. | 
| 8 |  |   (2) That the public utility is capable of efficiently  | 
| 9 |  |  managing and supervising the construction process and has  | 
| 10 |  |  taken sufficient action to ensure adequate and efficient  | 
| 11 |  |  construction and supervision of the construction. | 
| 12 |  |   (3) That the public utility is capable of financing  | 
| 13 |  |  the proposed construction without significant adverse  | 
| 14 |  |  financial consequences for the utility or its customers. | 
| 15 |  |  (g) The Commission shall issue its decision with findings  | 
| 16 |  | of fact and conclusions of law granting or denying the  | 
| 17 |  | application no later than 150 days after the application is  | 
| 18 |  | filed. The Commission may extend the 150-day deadline upon  | 
| 19 |  | notice by an additional 75 days if, on or before the 30th day  | 
| 20 |  | after the filing of the application, the Commission finds that  | 
| 21 |  | good cause exists to extend the 150-day period. | 
| 22 |  |  (h) In the event the Commission grants a public utility's  | 
| 23 |  | application for a certificate pursuant to this Section, the  | 
| 24 |  | public utility shall pay a one-time construction fee to each  | 
| 25 |  | county in which the Project is constructed within 30 days  | 
| 26 |  | after the completion of construction. The construction fee  | 
     | 
 |  | HB4383 Engrossed | - 18 - | LRB102 22689 SPS 31835 b |  
  | 
| 
 | 
| 1 |  | shall be $20,000 per mile of high voltage electric service  | 
| 2 |  | line constructed in that county, or a proportionate fraction  | 
| 3 |  | of that fee. The fee shall be in lieu of any permitting fees  | 
| 4 |  | that otherwise would be imposed by a county. Counties  | 
| 5 |  | receiving a payment under this subsection (h) may distribute  | 
| 6 |  | all or portions of the fee to local taxing districts in that  | 
| 7 |  | county. | 
| 8 |  |  (i) Notwithstanding any other provisions of this Act, a  | 
| 9 |  | decision granting a certificate under this Section shall  | 
| 10 |  | include an order pursuant to Section 8-503 of this Act  | 
| 11 |  | authorizing or directing the construction of the high voltage  | 
| 12 |  | electric service line and related facilities as approved by  | 
| 13 |  | the Commission, in the manner and within the time specified in  | 
| 14 |  | said order.
 | 
| 15 |  | (Source: P.A. 99-399, eff. 8-18-15.)
 |